SMED Case
Study
Glen Electric
– Single Minute Exchange of Die (SMED)
Glen Electric Ltd. based in Newry,
had embarked on a massive programme of implementing
lean manufacturing techniques that would enable them
to become as competitive on cost as their counterparts
in China. This meant that they needed to massively reduce
the led times from 4 weeks down to less than 1 week
where possible.
Inventories
carried at every stage of manufacture were a critical
point of their focus and in particular at the press
stage where several weeks of production requirement
were traditionally batched. The case study below illustrates
the impact that 2 days can have on a changeover of an
800T hydraulic press. Single Minute Exchange of Die (SMED) techniques were utilised in effecting the changes.
A small team of operators and support
staff were assembled to carry out an actual changeover
so that each element could be identified and quantified.
The data collected from the study was
then analysed using gantt charts before all possible
improvement opportunities were discussed. The reallocation
of tasks enabled each of the operators
to work simultaneously and without unnecessary walking
around the press. The revised allocation was then put
to the test with a resultant drop in Changeover time
from 75 minutes to 45 mins.
The impact of this will also have a
significance in terms of the overall capacity of the
press since the proposed introduction of a press supermarket
will require the press to change over much more frequently
that the current 2 changes per day.
Call us now on 01733 573437
Send
us an enquiry

|